Elevator Construction Schedule

The campus elevator construction schedule is as follows:

Building Elevator(s) Begins Ends
East Residence Hall 1 & 2 Complete
Fine Arts 1 Complete
Speech 1 Complete
Ottenheimer Library 3 Complete
SU “B” 1 Complete
Ottenheimer Library 2 Complete
Dickinson Hall 1 & 2 Complete
SCLB 1 & 2 Complete
Ottenheimer Library 1 2/24/11 4/15/11
Fribourgh Hall 1 4/18/11 6/3/11
Ross Hall 1 & 2 5/2/11 7/2/11
DSC 1, 2, & 3 5/9/11 5/13/11
Parking Deck 1 5/16/11 5/20/11
Administration South 1 5/23/11 6/24/11
Law School 1 & 2 5/23/11 5/27/11
ETAS 1, 2, & 3 5/30/11 6/3/11
Stabler Hall 1 & 2 6/20/11 6/24/11
Administration North 1 5/23/11 6/17/11
Updated 5.2.2011