Elevator Construction Schedule
The campus elevator construction schedule is as follows:
| Building | Elevator(s) | Begins | Ends |
|---|---|---|---|
| East Residence Hall | 1 & 2 | Complete | |
| Fine Arts | 1 | Complete | |
| Speech | 1 | Complete | Ottenheimer Library | 3 | Complete |
| SU “B” | 1 | Complete | |
| Ottenheimer Library | 2 | Complete | |
| Dickinson Hall | 1 & 2 | Complete | |
| SCLB | 1 & 2 | Complete | |
| Ottenheimer Library | 1 | 2/24/11 | 4/15/11 |
| Fribourgh Hall | 1 | 4/18/11 | 6/3/11 |
| Ross Hall | 1 & 2 | 5/2/11 | 7/2/11 | DSC | 1, 2, & 3 | 5/9/11 | 5/13/11 |
| Parking Deck | 1 | 5/16/11 | 5/20/11 |
| Administration South | 1 | 5/23/11 | 6/24/11 |
| Law School | 1 & 2 | 5/23/11 | 5/27/11 |
| ETAS | 1, 2, & 3 | 5/30/11 | 6/3/11 |
| Stabler Hall | 1 & 2 | 6/20/11 | 6/24/11 |
| Administration North | 1 | 5/23/11 | 6/17/11 |
Updated 5.2.2011