Data Warehouse

Completed
Implementation Phase
Expected Start Date
09/01/2017
Expected End Date
12/06/2018

The Data Warehouse is a key component of the UA Little Rock Quality Initiative.  The University has a strategic goal of utilizing data on student, recruitment, progress, success, and graduation to make operational decisions about University programs, policies and procedures.  The Data Warehouse is designed to provide data and address key metrics for University decision makers.

The University of Arkansas at Little Rock (UALR) launched a Decision Support System (DSS) implementation project in fall 2013 to provide support and tools that facilitate a data-informed culture of continuous improvement and demonstrate the university’s academic, economic, and societal impact to the city, state, and region.

WIP – work in progress, NS – not started
Milestone Target Date Status
Phase One: Solution Scoping Complete 9/15/17 Complete
Phase Two: Implementation & Testing – 10/1/2018
New Hires Complete 5/7/18 Complete
Dev – Test HW/SW Environment Set Up 5/11/18 Complete
Requirements / Data Models Complete 6/12/18 Complete
Production HW/SW Environment Set Up 6/22/18 Complete
UALR Staff Training Complete 6/25/18 Complete
ETL Development Training Complete 8/7/18 Complete
QI Reports and Dashboards Complete 8/23/18 Complete
Deployed to Production 10/1/18 Complete
Phase Three: Training & System Roll-out – 12/6/2018
Training Material Prep Complete 10/30/18 NS
User Training Complete 11/13/18 NS
System Rollout / Go-Live Complete 11/19/18 NS
Production Turnover Complete 12/6/18 NS
Data Warehouse/DSS Project Complete 12/6/18 NS